MIDTOWN REDEVELOPMENT AUTHORITY

 

Baldwin Park Neighborhood Streets

Reytec is the Prime Contractor to the Midtown Redevelopment Authority and responsible for traffic control, street lighting, pavement markings, pollution prevention, sitework/landscaping, demolition of existing concrete/asphalt paving (curbs, sidewalks, storm sewer), install concrete paving, stamped concrete sidewalks, curbs, install sanitary sewer, waterline, storm sewer, 20,000 square yards of 7” concrete paving.

 

Underground Utilities:

790 lf - 8” PVC Sanitary Sewer, Open Cut
325 lf - 10” PVC Sanitary Sewer, Open Cut
6,450 lf - 8” CL-52 DIP Water, Open Cut
550 lf - 8” Water 16” Steel Casing Jack & Bore
1,215 lf - 24” RCP C-76 CL III Storm Sewer, Open Cut
1,700 lf - 30” RCP C-76 CL III Storm Sewer, Open Cut

 

Contract Amount: $3,442,051.60

% Completed: 60%
Project Completion: 4/2006