Ella Paving from Pinemont to West Little York
Reytec is the Prime Contractor to the City of Houston and responsible for the complete project. Construction of ~5500LF of divided four (4) lane 57,000 square yards of 9” concrete street paving, curbs, esplanades, 30,000 cyd. road excavation, traffic signal systems, 13,500LF 9x5, 3x4, 6x5 concrete box culvert, RCP storm, sanitary sewer and domestic water supply.
Underground Utilities:
3,912 lf - 24” RCP Storm Sewer, Open Cut
308 lf - 30” RCP Storm Sewer, Open Cut
346 lf - 36” RCP Storm Sewer, Open Cut
219 lf - 3’x3’ Box Storm Sewer, Open Cut
1,019 lf - 5’x3’ Box Storm Sewer, Open Cut
110 lf - 5’x4’ Box Storm Sewer, Open Cut
1,322 lf - 6x3 Box Storm Sewer, Open Cut
973 lf - 6x5 Box Storm Sewer, Open Cut
4,618 lf - 8x4 Box Storm Sewer, Open Cut
5,286 lf - 9x5 Box Storm Sewer, Open Cut
2,994 lf - 8” Sanitary Sewer, Open Cut
6,351 lf - 8” Sanitary Sewer Remove & Replace
345 lf - 6” Watermain, Open Cut
1,120 lf - 8” PVC Watermain, Open Cut
8,130 lf - 12” PVC Watermain, Open Cut
253 lf - 16” PVC Watermain, Open Cut
Contract Amount: $8,620,628.00
Completion: 9/2007
|